  1. Overview
    1.  
      About the Veritas Access 3360 Appliance
    2.  
      Supported software
    3.  
      Access 3360 compute node and 5U84 storage shelves
    4.  
      Access 3360 compute node disk drives
    5. About the compute node control panel
      1.  
        About the System Status LED states
      2.  
        About the Power button LED states
    6.  
      Access 3360 compute node rear panel
    7.  
      5U84 storage shelf drawers and disk drives
    8.  
      5U84 storage shelf control panel
    9.  
      5U84 storage shelf rear panel
    10.  
      5U84 storage shelf RAID controller
    11.  
      5U84 storage shelf Expansion module
    12.  
      Cables and connectors
    13.  
      About IPMI configuration
  2. Pre-installation requirements
    1.  
      Customer-provided environment and supplies
    2.  
      Storage shelf shipping container contents
    3.  
      Compute node shipping container contents
    4.  
      Dimensions and determining rack locations
    5.  
      Best practices for rack installation
    6.  
      Heat dissipation guidelines
    7.  
      Cable length verification
    8.  
      Prerequisites for IPMI configuration
  3. Hardware installation procedures
    1.  
      Overview
    2.  
      Installing a storage shelf
    3.  
      Installing disk drives into a storage shelf
    4.  
      Installing the storage shelf bezels
    5.  
      Installing the compute node rack rails
    6.  
      Installing the compute node into a rack
    7.  
      Connecting the hardware to one compute node
    8.  
      Connecting the hardware to two compute nodes
    9.  
      Connecting Access nodes to the network
    10.  
      Connecting the power cords to the hardware
    11.  
      Turning on the hardware and verifying operation
    12.  
      Configuring the IPMI port
    13.  
      Accessing and using the Veritas Remote Management interface
  4. Appendix A. Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
    1.  
      Overview
    2.  
      Turning off the existing hardware
    3.  
      Installing the hardware
    4.  
      Connecting one Expansion shelf to the Primary shelf
    5.  
      Connecting two Expansion shelves to the Primary shelf
    6.  
      Connecting three Expansion shelves to the Primary shelf
  5. Appendix B. Adding Expansion Storage Shelves to an operating appliance that has at least one operating Expansion shelf
    1.  
      Overview
    2.  
      Turning off the existing hardware
    3.  
      Installing the hardware
    4.  
      Connecting one Expansion shelf to a system that has one existing Expansion shelf
    5.  
      Connecting two Expansion shelves to a system that has one existing Expansion shelf
    6.  
      Connecting one Expansion shelf to a system that has two existing Expansion shelves
  6. Appendix C. Configuring the disk space after adding one or more new Expansion Storage Shelves
    1.  
      Adding the disk space of an Expansion Storage Shelf from the Access Appliance shell menu

Installing the compute node into a rack

After the storage shelves and the compute node rails have been installed, you can install the compute node into the rack. These instructions apply to a one-node system and to a multi-node system.

To install the compute node into the rack

  1. Verify that the rails are securely attached.
    • Verify that the outer rail is securely attached to the rack.

    • Verify that the inner rail is securely attached to the compute node.

  2. Place the hardware in the front of the rack.
  3. Slide the blue tab forward to unlock the intermediate rail.
  4. Pull the intermediate portion of rail the rail forward. Ensure that the ball bearing retainer on the intermediate rail is locked forward.

    Note:

    You do not need to extend the rails as far as they can possibly extend. You only need sufficient space to place the hardware into the rails.

  5. Align the compute node inner rail to the intermediate rail in the rack. Slide the inner rail that is attached to compute node forward into the intermediate rail until a hard stop is encountered.

    The rail has a lock mechanism that prevents the hardware from being fully pushed into the rack.

  6. Slide the blue tab to unlock the rails and continue the sliding of the compute node into the rack.
  7. Secure the captive screws on the compute node ears.