Veritas Access 3360 Appliance Hardware Installation Guide

Last Published:
Product(s): Appliances (8.4, 8.3, 8.2)
Platform: Veritas 3360
  1. Overview
    1.  
      About the Veritas Access 3360 Appliance
    2.  
      Supported software
    3.  
      Access 3360 compute node and 5U84 storage shelves
    4.  
      Access 3360 compute node disk drives
    5. About the compute node control panel
      1.  
        About the System Status LED states
      2.  
        About the Power button LED states
    6.  
      Access 3360 compute node rear panel
    7.  
      5U84 storage shelf drawers and disk drives
    8.  
      5U84 storage shelf control panel
    9.  
      5U84 storage shelf rear panel
    10.  
      5U84 storage shelf RAID controller
    11.  
      5U84 storage shelf Expansion module
    12.  
      Cables and connectors
    13.  
      About IPMI configuration
  2. Pre-installation requirements
    1.  
      Customer-provided environment and supplies
    2.  
      Storage shelf shipping container contents
    3.  
      Compute node shipping container contents
    4.  
      Dimensions and determining rack locations
    5.  
      Best practices for rack installation
    6.  
      Heat dissipation guidelines
    7.  
      Cable length verification
    8.  
      Prerequisites for IPMI configuration
  3. Hardware installation procedures
    1.  
      Overview
    2.  
      Installing a storage shelf
    3.  
      Installing disk drives into a storage shelf
    4.  
      Installing the storage shelf bezels
    5.  
      Installing the compute node rack rails
    6.  
      Installing the compute node into a rack
    7.  
      Connecting the hardware to one compute node
    8.  
      Connecting the hardware to two compute nodes
    9.  
      Connecting Access nodes to the network
    10.  
      Connecting the power cords to the hardware
    11.  
      Turning on the hardware and verifying operation
    12.  
      Configuring the IPMI port
    13.  
      Accessing and using the Veritas Remote Management interface
  4. Appendix A. Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
    1.  
      Overview
    2.  
      Turning off the existing hardware
    3.  
      Installing the hardware
    4.  
      Connecting one Expansion shelf to the Primary shelf
    5.  
      Connecting two Expansion shelves to the Primary shelf
    6.  
      Connecting three Expansion shelves to the Primary shelf
  5. Appendix B. Adding Expansion Storage Shelves to an operating appliance that has at least one operating Expansion shelf
    1.  
      Overview
    2.  
      Turning off the existing hardware
    3.  
      Installing the hardware
    4.  
      Connecting one Expansion shelf to a system that has one existing Expansion shelf
    5.  
      Connecting two Expansion shelves to a system that has one existing Expansion shelf
    6.  
      Connecting one Expansion shelf to a system that has two existing Expansion shelves
  6. Appendix C. Configuring the disk space after adding one or more new Expansion Storage Shelves
    1.  
      Adding the disk space of an Expansion Storage Shelf from the Access Appliance shell menu

Customer-provided environment and supplies

For best ventilation, the rack cabinet:

  • Should be at least 100 cm (4 feet) from walls

  • Should be at least 100 cm (4 feet) from other cabinets on the front and back of the compute node and the storage shelves

The following list describes the necessary personnel and equipment that are needed at the installation site:

  • At least one person or a mechanical lift to move the compute node.

  • Three people or a mechanical lift to move each storage shelf.

  • A magnetic Philips-head screw driver to install the storage shelf rails into the rack.

  • A screwdriver with a 2mm Hex bit to secure the bezels to the front of each storage shelf drawer.

  • Cables to connect the compute node to your corporate network.

  • A USB-keyboard and a monitor to connect to the compute node.

  • A 19-inch rack with dual Power Distribution Units (PDUs) with 120VAC or 220VAC power input for the compute node.

  • A 19-inch rack with dual Power Distribution Units (PDUs) with 220VAC power input for the storage shelves.

Refer to the following section for more details.

See Heat dissipation guidelines.