Veritas™ 5360 Appliance Hardware Installation Guide
- Hardware overview
- About the 5360 Appliance control panel
- Preinstallation requirements
- Hardware installation procedures
- Appendix A. Adding Expansion Storage Shelves to an operating appliance that does not have any Expansion shelves
- Appendix B. Adding Expansion Storage Shelves to an operating appliance that has at least one operating Expansion shelf
- Appendix C. Configuring the disk space for new Flex Expansion Storage Shelves
Customer-provided environment and supplies
For best ventilation, the rack cabinet:
Should be at least 100 cm (4 feet) from walls
Should have at least 100 cm (4 feet) from other cabinets on the front and back of the appliance and the storage shelves
Data centers with two-foot spaces in the front and in the back of the appliances are acceptable with proper cooling and ventilation.
Refer to the following section for more details.
See Heat dissipation.
The following describes the necessary personnel and equipment that are needed at the installation site:
At least three people or a mechanical lift to move the appliance and the storage shelves.
Cables to connect the appliance to your corporate network.
A USB-keyboard and a monitor to connect to the appliance.
A 19-inch rack with dual Power Distribution Units (PDUs) with 120VAC or 220VAC power supplies for the compute node.
A magnetic Philips-head screw driver to install the storage shelf rails into the rack.
A screwdriver with a 2mm Hex bit to secure the bezels to the front of each storage shelf drawer.
A 19-inch rack with dual Power Distribution Units (PDUs) with 220VAC power input for the storage shelves.