Veritas™ Resiliency Platform 2.2 Solutions for Applications
- Overview of Resiliency Platform
- Managing applications using Resiliency Platform
- Managing InfoScale applications using Resiliency Platform
- Managing resiliency groups
- About resiliency groups
- Preparing for disaster recovery configuration
- About replication technologies used in disaster recovery of applications
- Configuring DNS server settings for a data center
- Configuring resiliency groups for remote recovery
- Rehearsing DR operations to ensure DR readiness
- Performing disaster recovery operations
- Monitoring and reporting assets status
- Monitoring risks
- Managing activities and resiliency plans
- Managing activities
- Managing resiliency plans
- Creating a new resiliency plan template
- Managing evacuation plans
- Appendix A. Troubleshooting
Performing cleanup evacuation rehearsal
After you have performed the rehearse evacuation operation successfully to verify if all your assets from the production data center can evacuate to the recovery data center, you can use the cleanup evacuation rehearsal operation to clean up the rehearsal virtual machines and its volumes in the VBS or resiliency groups.
All temporary objects that are created during the rehearse evacuation operation are now deleted.
During the rehearse evacuation operation, if any virtual machines are in ERROR state, then during the cleanup evacuation rehearsal operation, these virtual machines and their volumes are not deleted. You need to manually delete them. Similarly if the recovery data center is Cloud, then manually delete the instances which are in ERROR state.
To perform the cleanup rehearsal of an evacuation plan
- Navigate
Automation Plans (menu bar) > Evacuation Plans
- For the required data center, click on the vertical ellipses and select Cleanup Evacuation Rehearsal.