Veritas™ Resiliency Platform 2.2 Solutions for Microsoft Hyper-V
- Section I. Overview of Resiliency Platform
- Section II. Preparing your environment
- Using array-based replication
- Managing disaster recovery network mapping
- Using array-based replication
- Section III. Working with resiliency groups
- Managing resiliency groups
- Configuring resiliency groups for remote recovery
- Managing virtual machines for remote recovery (DR) using 3rd party replication technology
- Managing virtual machines for remote recovery (DR) in Amazon Web Services
- Section IV. Managing disaster recovery
- Managing resiliency plans
- Creating a new resiliency plan template
- Monitoring risks, reports, and activites
- Managing evacuation plans
- Appendix A. General troubleshooting
- Appendix B. Sample policy and trust relationships for AWS
Generating an evacuation plan
Using the Resiliency Platform console you can generate an evacuation plan that lets you evacuate all the assets from the production data center to the recovery data center.
Using the evacuation plan template you can define the sequence in which the virtual business services (VBS) should be migrated from the production data center to the recovery data center. Resiliency groups that do not belong to any VBSs, are appended at the end of the evacuation plan workflow after the VBS.
By default only one priority group is created. To add more priority groups, click
and click the button. You can drag and drop the VBSs into different priority groups.removes all priority groups except one. All VBSs are moved into a single priority group.
If an asset within a VBS or a resiliency group fails to recover, the evacuation plan skips the asset and continues the process for the remaining assets. To do this you need to select the
check box while creating the evacuation plan.If any VBSs and resiliency groups do not fit the evacuation plan criteria, a message is displayed. We recommend that you fix the issues before creating the plan.
Only users with Manage Evacuation Plans permission can create and run the evacuation plans.
To generate an evacuation plan
- Prerequisites
- Navigate
Automation Plans (menu bar) > Evacuation Plans
- Select Evacuation Plans.
- For the required data center click Generate Plan.
- Review the message if any and click Next.
- Click Change Priority if you want to add more priority groups. Click Submit.
See Performing rehearse evacuation.
More Information