Veritas NetBackup™ Appliance Upgrade Guide
- Introduction
- Upgrade planning
- Pre-upgrade tasks
- Performing the upgrade
- Post upgrade tasks
- Troubleshooting
Upgrade time estimation
Table: Upgrade scenarios and related time estimations
Model | Upgrade path | Estimated base time | Additional time considerations |
---|---|---|---|
5220 | 2.6.1 -> 3.1 2.6.1.x -> 3.1 2.7.x -> 3.1 3.0 -> 3.1 | 2 - 2.5 hours |
|
5230 | 2.6.1 -> 3.1 2.6.1.x -> 3.1 2.7.x -> 3.1 3.0 -> 3.1 | 2 - 2.5 hours |
|
5330 | 2.6.1 -> 3.1 2.6.1.x -> 3.1 2.7.x -> 3.1 3.0 -> 3.1 | 2 - 2.5 hours | For appliances with Expansion Storage Shelf units, add 15 minutes for each unit. |
5240 | 2.7.3 -> 3.1 3.0 -> 3.1 | 1.5 - 2 hours | N/A |
For all the upgrade scenarios, refer to the following:
Add 10 minutes for every 350,000 jobs on the master server. For example, add 30 minutes to a master server with a job list containing 1 million records.
Add 5 minutes for every 250 VLANs that you have configured.